New Cold Sinter Screening System and Hearth Layer Feeding arrangement at Sinter Plant-II. Civil Work, Structural Work, Erection of Plant & Equipment and Utilities.
Revamping and restoration of Gas Cleaning Plant for Blast Furnace.
Erection, Testing & Commissioning of 05 nos. Oxygen / Nitrogen Turbo Compressors of Capacity-12500 NM3 and Pressure 31 bar, Make Kazan (Russia) with CS & SS pipeline work.
Fabrication, Erection and Testing of CS pipeline for Oxygen at pressure 31 bar from OP-II to SMS-I. Approximately 4000 RM.
Fabrication, Erection and Testing of Oxygen PRMS (CS, SS & Copper piping) for Blast Furance - II & V.
Up-gradation of Nitrogen Network Phase-I Dismantling of existing facility and Erection of New Equipments and Pipeline work.
Up-gradation of Nitrogen Network Phase-II Design & Engg, Civil Work, Structural Work, Supply of Plant & Equipment and Utilities, Erection and Commissioning on Turnkey basis.
Installation of 04 nos. of 25-ton CNC Lathe Roll Turning Lathe for Universal Rail Mill (PKG-142-01).
Installation of Online Eddy Current Testing Machine and Optical Visual Inspection System Supplied by NDT Technologies, Canada at Rail Mill including foundation design and Civil Work.
Installation of 02nos. Of 5-ton CNC Lathe Machines Supplied by Hankook Machine Tools Co., Korea in Roll Turing Shop including foundation design and Civil Work.
Installation of 25-ton CNC Lathe Machines Supplied by Hankook Machine Tools Co., Korea in Roll Turing Shop including foundation design and Civil Work.
Relocation of Mechanical Repair Shop & Quenching Car Repair Shop of CO&CCD including foundation design and Civil Work.
Infrastructure Facilities For 2 X 1250 TPD Oxygen Plant - Provision of Water Facilities (Works Package) at BSP, Bhilai - Erection of Mechanical Plant & Equipment and Civil Work.